Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/20/2012 |
Comment Period | 05/12/2013 |
Decision | 05/2013 (Estimated) |
Implementation | 06/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tonasket Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
WSP Tunk Mountain Communications Site
Decision Signed Date: 05/07/2013
Legal Notice Date: 05/12/2013
Forests:
Okanogan-Wenatchee National Forest
Districts:
Tonasket Ranger District
States:
Washington
Counties:
Okanogan
Legal Land Description:
Section 8, Township 35 North, Range 29 East, W.M.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Phillip Christy
1 West Winesap
Tonasket, WA 98855
509-486-5137
pchristy@fs.fed.us
Last Updated: 5/31/2013