Sawtooth Conifer Transplants
It provides areas that the public can be directed to for conifer sapling transplants via permit or contract. About 295 acres are authorized for sapling removal. All work done by hand.
Project Summary
Location Summary:
The first area is 145 accres along FSR 30, 24 and 3000-585. The second area is 150 acres along FSR 3000-580, also known as the Berryfield Access Picnic Area.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/09/2013 |
Decision | 01/2014 (Estimated) |
Implementation | 04/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (8), 36 Cfr 220.6(D)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mount St. Helens National Volcanic Monument
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products
Project Activity:
Forest Vegetation Improvements; Special Products Sales
Current Status:
Completed
Project Decision Information
Sawtooth Conifer Transplants
Decision Signed Date: 01/08/2014
Forests:
Gifford Pinchot National Forest
Districts:
Mount St. Helens National Volcanic Monument
States:
Washington
Counties:
Skamania
Legal Land Description:
Sections 15 and 22, T7N, R8E, Willamette Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ben Hoppus
42218 N.E. Yale Bridge Rd.
Amboy, WA 98601
509-395-3405
bhoppus@fs.fed.us
Last Updated: 2/10/2014