Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/08/2025 |
Decision | 07/2025 (Estimated) |
Implementation | 08/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Manchester Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Dispersed Recreation Mgmt.; Special Use Authorizations; Trail Management
Current Status:
Completed
Project Decision Information
Dover Parking Lot Special Use Permit
Decision Signed Date: 07/25/2025
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Manchester Ranger District
States:
Vermont
Counties:
Windham
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jennifer Edmonds
2538 Depot Street
Manchester Center, VT 05255
802-747-6746
jennifer.edmonds@usda.gov
Last Updated: 7/28/2025