Finley HFRA Thin
Project would include commercial and non-commercial fuel reduction thinning and burning on approximately 153 acres in the Finley Canyon area.
Project Summary
Location Summary:
In the vicinity of Finley Canyon
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/04/2006 |
Objection Period Start | 07/08/2008 |
Decision | 09/2008 (Estimated) |
Implementation | 09/2008 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Categorical Exclusion:
32.2 (10)
Special Authority:
Hfra Title I: Wildland-Urban Interface
Lead Management Unit:
Methow Valley Ranger District
Notice and Comment Regulation:
218
Project Purpose:
Vegetation Management (Other Than Forest Products); Fuels Management; Forest Products
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Finley HFRA Thin
Decision Signed Date: 09/04/2008
Forests:
Okanogan-Wenatchee National Forest
Districts:
Methow Valley Ranger District
States:
Washington
Counties:
Okanogan
Legal Land Description:
Sections 20, 21, 28, and 29, T33N, R23E, WM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Arlo VanderWoude
24 West Chewuch Road
Winthrop, WA 98862
509-996-4049
avanderwoude@fs.fed.us
Last Updated: 9/9/2008