Whiskey Creek Restoration
Whiskey Creek, a tributary to Crow Creek, had an assumed flood that caused an avulsion. Project work is designed to return flow to the natural channel and reduce potential for future problems with roadwork.
Project Summary
Location Summary:
Whiskey Creek, a tributary to Crow Creek in the Preuss range.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/23/2025 |
Decision | 06/2025 (Estimated) |
Implementation | 07/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Caribou-Targhee National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Current Status:
Completed
Project Decision Information
Whiskey Creek Restoration
Decision Signed Date: 06/24/2025
Forests:
Caribou-Targhee National Forest
Districts:
Montpelier Ranger District
States:
Idaho
Counties:
Bear Lake
Legal Land Description:
T11S R45E, NW1/4 Section 34
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kara Green
1405 Hollipark Drive
Idaho Falls, ID 83401
208-547-1110
kara.green@usda.gov
Last Updated: 6/24/2025