Rainey Creek Trail Bridges
The project proposes to install 5 bridges at creek crossings on the Rainey Creek Trail. The proposed bridges would stop further damage to the stream channel and provide a way for users to safely cross the creek.
Project Summary
Location Summary:
The project is located about 6 miles east, northeast of Swan Valley, ID in the Rainey Creek drainage.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/17/2022 |
Comment Period | 11/17/2022 |
Decision | 01/2023 (Estimated) |
Implementation | 06/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Palisades Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Recreation Management
Project Activity:
Trail Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
Rainey Creek Trail Bridges
Decision Signed Date: 01/26/2023
Forests:
Caribou-Targhee National Forest
Districts:
Palisades Ranger District
States:
Idaho
Counties:
Bonneville
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Colby Jacobson
3659 East Ririe Highway
Idaho Falls, ID 83401
208-547-1106
colby.jacobson@usda.gov
Last Updated: 1/26/2023