Gateway West 230/500 kv Transmission Line Project
Idaho Power and Rocky Mountain Power propose to construct electric transmission lines from the proposed Windstar Substation near the Dave Johnston Power Plant at Glenrock, WY to the proposed Hemingway substation near Melba, Idaho
Project Summary
Location Summary:
Montpelier District, CTNF - northern most corridor designated in the Caribou NF Plan, Doulgas Distict MBRNF northern most corridor designated in the MBR Plan.
Project Milestones:
Milestone | Date |
---|---|
NOI in Federal Register | 05/16/2008 |
DEIS NOA in Federal Register | 07/29/2011 |
FEIS NOA in Federal Register | 04/26/2013 |
Decision | 09/2013 (Estimated) |
Implementation | 11/2013 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Medicine Bow-Routt National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Gateway West 230/345/500-kV Transmission Line Project Record of Decision
Decision Signed Date: 09/18/2013
Legal Notice Date: 09/26/2013
Gateway West 230/345/500-kV Transmission Line Project
Decision Signed Date: 09/23/2013
Legal Notice Date: 09/26/2013
Forests:
Medicine Bow-Routt National Forest; Caribou-Targhee National Forest
Districts:
Douglas and Thunder Basin Ranger District; Montpelier Ranger District
States:
Idaho; Wyoming
Counties:
Bear Lake; Albany; Converse; Natrona
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Misty Hays
2468 Jackson Street
Laramie, WY 82070
307-358-4690
mahays@fs.fed.us