Rainey Creek Vegetation Restoration Project
Use prescribed fire and mechanical thinning to improve the vegetative/brush diversity and resilience within juniper and mountain mahogany. Reduce hazardous fuels adjacent to private property and along the Rainey Creek road for public safety.
Project Summary
Location Summary:
Township: 2N
Range: 44E
Sections: 14, 15, 20 - 29
This project is located 2 miles east of Swan Valley.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/06/2014 |
Decision | 02/2016 (Estimated) |
Implementation | 05/2016 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Palisades Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Fuels Management; Wildlife, Fish, Rare Plants; Vegetation Management (Other Than Forest Products)
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements
Current Status:
Cancelled
Forests:
Caribou-Targhee National Forest
Districts:
Palisades Ranger District
States:
Idaho
Counties:
Bonneville
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tracy Hollingshead
3659 East Ririe Highway
Idaho Falls, ID 83401
208-523-1412
tracy.hollingshead@usda.gov
Last Updated: 6/18/2024