Gulf Power North Florida Resiliency Connection (NFRC) Project
The project proposes to connect the Florida Power and Light Company's (FPL) Raven Substation in Columbia County, Florida, to Gulf Power Company's (GPC) Sinai Substation in Jackson County, Florida.
Project Summary
Location Summary:
Located in compartments 201, 216, 218, 221, 222, 223,and 224 of the Apalachicola National Forest.
Project Milestones:
Milestone | Date |
---|---|
NOI in Federal Register | 05/08/2019 |
DEIS NOA in Federal Register | 09/2019 (Estimated) |
FEIS NOA in Federal Register | 11/2019 (Estimated) |
Objection Period Start | 10/2019 (Estimated) |
Decision | 12/2019 (Estimated) |
Implementation | 12/2019 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Wakulla Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Cancelled
Forests:
National Forests In Florida
Districts:
Wakulla Ranger District
States:
Florida
Counties:
Leon
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sherry Gaston
57 Taff Drive
Crawfordville, FL 32327
850-926-3561ex t6511
sgaston@fs.fed.us
Last Updated: 12/6/2019