FLEC Oosterneck Road Project
The project would install approximately 1,840 feet of three phase distribution powerline with approximately 10 new power poles and remove approximately 640 feet of electric line near Oosterneck Road.
Project Summary
Location Summary:
The project is located approximately 4 miles east of Tellico Plains, TN.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/06/2021 |
Decision | 05/2021 (Estimated) |
Implementation | 06/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tellico Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
FLEC Oosterneck Road Project
Decision Signed Date: 05/10/2021
Forests:
Cherokee National Forest
Districts:
Tellico Ranger District
States:
Tennessee
Counties:
Monroe
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Justin Feeman
250 Ranger Station Rd
Tellico Plains, TN 37385
423-397-8455
SM.FS.R8chertelcom@usda.gov