Revised Trapper Project
A Supplemental Environmental Assessment will be prepared to disclose effects of harvesting timber on about 33 acres already under contract and to respond to analysis deficiencies identified by the 2011 U.S. District Court decision.
Project Summary
Location Summary:
About 13 miles NE of Blue River, OR, adjacent to FS Road 1517.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/11/2013 |
Comment Period | 03/17/2014 |
Objection Period Start | 05/19/2014 |
Decision | 07/2014 (Estimated) |
Implementation | 09/2014 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Lead Management Unit:
McKenzie River Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Forest Products; Wildlife, Fish, Rare Plants
Project Activity:
Road Maintenance; Timber Sales (Green)
Current Status:
Completed
Forests:
Willamette National Forest
Districts:
McKenzie River Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
T14S, R5E, Sections 34 and 35, W.M.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Cheryl Friesen
57600 McKenzie Hwy
McKenzie Bridge, OR 97413
541-822-7226
cfriesen@fs.fed.us
Last Updated: 7/15/2014