Clarkia Work Center Wastewater Treatment Facility
Construct a subsurface wastewater treatment and disposal system for the St. Joe Ranger District's Clarkia Work Center.
Project Summary
Location Summary:
Map #8 - Clarkia Work Center on the St. Joe Ranger District near Clarkia, Idaho
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/19/2009 |
Decision | 03/2010 (Estimated) |
Implementation | 07/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (3), 36 Cfr 220.6(D)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
St. Maries Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction
Current Status:
Completed
Project Decision Information
Clarkia Work Center Wastewater Treatment Facility - Letter to File
Decision Signed Date: 03/12/2010
Forests:
Idaho Panhandle National Forest
Districts:
St. Maries Ranger District
States:
Idaho
Counties:
Shoshone
Legal Land Description:
Section 6, T42N, R2E, BM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Cornie Hudson
222 S. 7th St., Suite 1
St. Maries, ID 83861-0407
208-245-2531
chudson@fs.fed.us
Last Updated: 3/16/2010