White River Aspen Management Project

The WRNF is proposing to conduct vegetation management activities (mechanical and prescribed fire) within forest stands that contain aspen. Management would improve the resiliency of aspen forests to disturbance agents and improve wildlife habitat.

Location Summary

Treatments could occur in forests containing aspen that area within Forest Plan Management Areas 4.2, 4.23, 4.3, 4.32, 5.12, 5.13, 5.4, 5.41, 5.42, 5.43, 5.5, 7.1, 8.21, 8.25, and 8.32.

District: White River National Forest All Units

Project Milestones

MilestoneDate
Scoping Start02/19/2021
Comment Period02/19/2021
Objection Period Start11/01/2022 (Estimated)
Decision03/01/2023 (Estimated)
Implementation06/01/2023 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public

https://www.fs.usda.gov/project/?project=59419