Uinta Basin Railway Project

Withdrawal of the Forest Service (FS) decision on this project on 1/17/2024 was in response to a ruling by the U.S. Court of Appeals for the District of Columbia Circuit. The FS decision would have authorized 12 miles of the railway across NFS lands.

Location Summary

The preferred route would travel from Kyune, UT to Myton, UT, passing south of Duchesne, UT, along Indian Canyon. About 12 miles of the route would be located on FS lands.

District: Duchesne Ranger District

Project Milestones

MilestoneDate
NOI in Federal Register06/19/2019
DEIS NOA in Federal Register10/30/2020
FEIS NOA in Federal Register08/06/2021
Objection Period Start11/03/2021
Decision08/01/2022 (Estimated)
Implementation08/01/2023 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public

https://www.fs.usda.gov/project/?exp=overview&project=56603